Design Qualification of Colloid Mill

Colloid Mill

The design of colloid Mills is based on years of experience in wet communication, homogenization, emulsification, dispersion, fluidization mixing, etc.

The principle of the Colloid Mill is based on the Stator /Rotor Principle. The stator is ring-shaped with two different staggered special design tooth stages and conical shape tuning inside the stator with a special shape helical tooth system. The initial Rotor Stage is shaped with impeller blades as a preliminary drum, seizing the material, pre-breaking in, and throwing it into the first station tooth stage. The product is fed to the operating area of a Rotor, having a speed of approximately 3000 R.P.M. by a specially designed feed device. The product is processed by high shear, pressure, and friction between the Stator and Rotor, besides the high shear, beating, collisions, bombarding, and friction, the product is exposed to intense vibration which exerts its force in it through pressing and realizing actions. At the last stage of processing, the product is exposed to a basic oscillating frequency of 6000 Hz. The first upper oscillation of this stage lies with 18000 Hz utmost within the supersonic region, which explains high efficiency. The processed product continuously leaves the mill through the drain pipe, if required, it can be recirculated.

Due to the slightly deviating tapering of the milling surfaces of the stator and rotor, the annular gap becomes narrower towards the discharge section. The special design facilitates adjustment of the grinding gap by an exterior screw even during operation.

Control / Electrical Panel

Operating Control Panel

The Non-Flame proof control panel is made of MS covered with SS cover. It is located on the Machine.

The control panel contains.

START / STOP Switch

Design Qualification of Colloid Mill

OBJECTIVE

To design, engineer, and supply the Colloid Mill and to provide assurance that the machine is manufactured and complies with the Scope of Supply.

To prove that each operation proceeds as per the design qualification and the tolerances prescribed there in the document are the same at utmost transparency.

The scope of this qualification document is limited to the Design Qualification of Colloid Mill.  This qualification document is part of a validation activity for the Colloid Mill.

RESPONSIBILITIES

CLIENT: To Check and Approve the design qualification.

MANUFACTURER

To design, engineer, and provide the complete technical details of the equipment pertaining to its design qualification viz.

  • Machine overview,
  • General arrangement drawing,
  • Equipment orientation with layout,
  • Specifications of the sub-components/ bought out items, and their make, model & quantity, and backup records/ brochures,
  • Details of Utilities,
  • Material of construction of all components
  • To confirm the safe delivery of the equipment to the user site.

To ensure that no un-authorized and or unrecorded design modifications shall take place. If at any point in time, any change is desired in the mutually agreed design, Change control procedure shall be followed and documented.

To ensure the proper installation and commissioning of the equipment.

TECHNICAL SPECIFICATIONS OF COMPONENTS & SUB-COMPONENTS USED / BOUGHTOUTS

DescriptionSpecification
1. Equipment Description
NameColloid Mill
Make
ModelCPM CM 3 WJ
Hooper Capacity15 Liters
Particle Size Reduction5-10 micron
Overall dimensions1200 mm(H) X 410 mm(W) X 680 mm(L)
2. Main  Motor
TypeTEFC, FLP, 3 Phase induction motor
ModelFlange Mounted
MakeCrompton Greaves
RPM2850
Power Rating3 HP /     / 415 V / 50Hz / 2.2 KW
3. Starter
TypeSDS – 31403
ModelFlange Mounted
Power Rating3 HP / 415 V
MakePCG
START / STOP Switch01 Nos. Each

DETAILS OF UTILITIES

DESCRIPTION

SPECIFICATIONS

Electrical connectionTo be provided

MATERIAL OF CONSTRUCTION

COMPONENT DESCRIPTIONMOC
HopperSS 316
Circulating pipe with DrainSS316
Lid(Hopper)SS316
RotorSS316
StatorSS316

ENCLOSURES

DescriptionDrawing No.
General arrangement drawing of Colloid Mill 

 

CHANGE CONTROL PROCEDURE

Change in the agreed design shall be addressed through the well-defined Change control procedure.

DESIGN QUALIFICATION REPORT

APPENDIX

cGMPcurrent Good Manufacturing Practices
GEPGood Engineering Practices
MSMild steel
NFLPNon-Flame Proof
SSStainless Steel
KWKilo Watt
DQDesign Qualification

For More Pharma Updates Visit –https://pharmaguidances.com

About Pharma Editor

Check Also

Unlocking Success with User Requirement Specification: Coating Machine URS

Unlocking Success with User Requirement Specification: Coating Machine URS In any project or system development, …