Performance Qualification Protocol of Tunnel Sterilizer

Performance Qualification Protocol of Tunnel Sterilizer

Tunnel Sterilizer Description:

Sterilizing and depyrogenating tunnel enables the integration of the process of sterilization and depyrogenation of washed empty vials for sterile, continuous automatic filling in which all steps are performed under Grade A conditions.

The Tunnel is comprised of four zones, i.e. Drying zone, sterilizing zone, cooling zone, and Stabilizing zone.

Drying, cooling, and stabilizing zones are essential once-pass-through Laminar flow units comprising standard features, Pre-filters, motor blower assembly, and HEPA filters.

Extract and exhaust blowers are provided under the conveyor connected to the ambient using a common duct.

Vials are transferred by a stainless steel Wire Loop conveyor through drying, sterilizing, cooling, and stabilizing zones under non-turbulent class ISO 5 fresh air.

Container-controlled partition wall adjustment panels are provided at the entry and exit of the sterilizing zone.

In the feed area air taken from the room is prefiltered and aspirated by a blower through a HEPA filter. A laminar flow of air is sent vertically down onto the containers.

Containers passed nearer to the sterilizing zone are preheated up to 90-110°C by the hot air bleeding out of the sterilizing zone. the air along with water vapor is picked up underneath the conveyor belt by the extract blower and ejected outside.

Dried containers are moved over to the sterilizing zone. The sterilizing zone mainly comprises of resistance heating elements, HEPA filters, and temperature-regulating devices.

Hot filtered air is re-circulated in the sterilization zone, which sweeps the containers from top to bottom.

Differences exist in the hot air temperature and conveyor speed settings depending on the total mass of the glass required to be sterilized and cooled.

Equal pressure drop across the filter enables in creation of an extremely even distribution of air circulation.

This uniformly distributed hot air sterilizes and depyrogenates the containers. In the cooling and stabilization zones, containers are subjected to a Laminar flow of HEPA-filtered air taken from the room.

The airflow is profiled in such a way that the glass temperature as it excited the sterilizing zone would be transitioned at a nearly linear rate.

A stabilizing zone is used as a transition area separating the critical filling area and washing area.

A conveyor system is controlled by the container accumulation at the infeed and the set temperature for the conveyor starts.

SS wire Loop conveyor driven by a gear motor with AC frequency controlled drive and tension roller for maintaining the correct tension of the conveyor belt.

Control and recording systems for the parameters governing the sterilizing process such as air temperature, belt speed, and holding time are standard features.

The sterilizing and depyrogenating tunnel is equipped and controlled with an Allen Bradley PLC and MMI (Man Machine Interface) which in conjunction with RTDs, Infeed / Outfeed Proximity switches, Dot Matrix printers, and frequency converter (Variable speed drive) make the operations fully automatic.

Mode of operation enables one to opt a) Auto mode or b) Maintenance mode.

In the Auto mode, the operation of the tunnel is fully automatic. The tunnel starts and stops at a predetermined time. All blowers are running continuously except sterilizing zone heaters, which cut off when the temperature reaches the set temperature.

In the Maintenance mode, all operations are being done manually.

TABLE OF CONTENTS

Description
Protocol Approval
Objective
Scope
System Description
Responsibilities And Identification Of Execution Team
Test Procedures
Recording Of Observations
Discrepancy And Corrective Action Report
Compilation, Review And Summary Report
Appendix
Requalification Criteria

PROTOCOL APPROVAL

The signing of this approval page of the protocol indicates agreement with the qualification approach described in this document. If any modification in the equipment qualification approach becomes necessary, a revision through change control shall be prepared, checked, and approved. This protocol cannot be executed until approved by the personnel. 

OBJECTIVE

The objective of this protocol is to provide a high degree of assurance in the sterilization and depyrogenation process, using a Tunnel sterilizer supplied by _______________________. The sterilizer is used to sterilize/depyrogenate glass vials (both molded and tubular) ranging from 5ml vials to 20ml vials.

Consecutive 3 runs for Heat penetration studies shall be carried out on each type of vial. These heat penetration studies shall include a Bacterial Endotoxin challenge study using Bacterial Endotoxin spiked vials (containing 104 EU/vial). The placement of the vials with the Endotoxin indicator in the vial load under test shall be in such a way that simulation of the worst-case consideration and normal load pattern can be established at a time.

Estimation of the FH value achieved during the sterilization hold period at each temperature-mapping probe. Biological indicators are not used as the intended cycle is for depyrogenation at a very high temperature and survival of the microorganisms is not possible after the depyrogenation cycle.

SCOPE

This protocol applies to the Tunnel sterilizer installed in the vial washing room of Production (sterile) area.

To be performed after the completion and authorization of Operational Qualification.

To be performed at the time of relocation or Requalification.

RESPONSIBILITIES AND IDENTIFICATION OF EXECUTION TEAM

Responsibilities: The group is comprised of representatives from each of the following departments and they shall be responsible for the overall compliance with this protocol. 

DepartmentResponsibility
ProductionExecute the validation activity & provide the necessary support
Engineering & UtilityParticipate & provide the necessary support for the validation activity
Quality ControlTesting of samples as per the test procedures
Quality AssuranceMonitoring, sampling & reviewing the validation activities.

Identification of Executors: The personnel involved in the execution of this protocol shall be recorded Name, Designation, Signature, and Date.

TEST PROCEDURES

Test procedures are followed to qualify the equipment for its performance.

Measurement of Airflow Velocity

Tools required: Calibrated Anemometer.

Test procedure:

Ensure that the equipment is ON except for heating before the start of the observations before 30 minutes.

Calculate the number of location by using the following formula. Distribute all the locations equally for each filter outlet.

Number of locations = square root of 10 times of area in square meters but no less than 4, we have considered 4 sampling points for each filter.

The airflow velocity should be measured at approximately 150 mm to 300 mm from the filter face by using a calibrated Anemometer. The measuring time at each location should be also sufficient to ensure a repeatable reading.

Record a minimum of 3 readings in each location and calculate the average measured velocity. Record the calibration details of the instrument used for measurement and attach the calibration certificate.

Acceptance criteria:

For Drying zone: Airflow velocity across the HEPA filter should be within the range of 98 ± 20 feet / minute [0.5± 0.1 m/sec]

For Sterilising zone/Heat zone: Airflow velocity across the HEPA filter should be within the range of 157 ± 20 feet/minute [0.8± 0.1 m/sec].

For Cool zone: Airflow velocity across the HEPA filter should be within the range of 118 ± 20 feet / minute [0.6± 0.1 m/sec].

Differential Pressure Test

Tools required: Calibrated Magnehelic Gauge / Photohelic gauges.

Test procedure: Observe the differential pressure across the zones through the Magnehelic Gauge / Photohelic gauge and note down the reading before operation and during operation. Repeat the procedure for two more times.

Acceptance criteria:

Magnehelic gauge should show the reading at ‘0’ before operation.

During operation,

For Drying Zone: equal to or above2 MMWG.

For Sterilising zone: equal to or above 25 MMWG

For Cool zone: equal to or above 25 MMWG

Installed Filter System Integrity and Leakage Test (DOP/PAO Test)

Tools required: Aerosol generator, Aerosol Photometer (Calibrated), and Dioctyl pthalate or PAO Liquid (Poly Alpha Olefin).

Test procedure:

Operate the Tunnel steriliser as per the SOP.

Position the Aerosol generator and introduce Aerosol into the upstream air, ahead of the HEPA filters, at the concentration of 80-100 mg per litre of air at the filter’s designed airflow rating and set the instrument at 100% concentration.

Scan the downstream side of the filter with probe at scanning rate not to exceed 15cm2/Second. The probe should be held at a maximum distance of 5cm from the down stream filter face. Scanning should be performed over the entire downstream face of each filter, the perimeter of each filter, the seal between the filter frame and the grid structure, including its joints. Measurements of the aerosol upstream of the filters should be repeated at a reasonable time intervals between and after scanning for leaks, to confirm the stability of the challenge aerosol concentration.

Record the observations. Record the details of the instruments used including its calibration status, filter identification number and upstream and downstream concentration of Dioctyl pthalate/ PAO. Attach the calibration certificate of the photometer.

Acceptance criteria: Designated leaks are deemed to have occurred where a reading greater than 10−4 (0.01%) of the upstream challenge aerosol concentration. Alternative acceptance criteria may be agreed based on the filter efficiency.

Airflow Pattern Test

Tools required: Dry Ice.

Test procedure: Take Dry Ice and check for airflow direction in the zones. Observe the direction of the flow and the same shall be recorded.

Acceptance criteria:

The stream of air should be unidirectional and non-turbulent up to the working zone.

Drying zone: airflow towards the vial washing side.

Sterilising zone: airflow towards the drying zone.

Cool zone: airflow towards Cooling zone and airflow from Vial filling side.

Non-Viable Particle Count Test

Tools required: Calibrated Air borne particulate counter.

Test procedure:

Calculation of Measuring Points (Sampling Locations)

Calculate the number of location by using the following formula. Distribute all the locations equally in the clean zone.

Number of locations = Square route of the area in meters

Sampling:

Tunnel sterilizer blowers shall be in continuous operation for at least 30 minutes prior to performing these tests. AHU of the particular room should also be in operation.

Sampling shall be done at rest conditions at pre-determined locations.

The non-viable particulate counts shall be done before and after the de-pyrogenation cycle. If the trails are conducted continuously on the same day, then the particulate count are taken before starting the first trial and after the completion of last trial.

Set the particle counter in ISO mode. Position the sampling probe towards airflow at work level and Sample at least 3 cycles for each location. Each cycle should be Approx. 28 litres/minute.

Paste the printouts generated by the particle counter on A4 page and shall be photocopied.

Verify the printouts for all calculations and acceptance criteria as mentioned below. Attach the photocopies of the same to the annexure –1. Attach the calibration certificate of Particle Counter.

Acceptance criteria:

All the readings of the test should pass the below-mentioned criteria.

The maximum permitted number of particles/m3 equal to or above 0.5μm is 3500 and 5μm is 20.

Heat Distribution Study For Empty Chamber

Tools required: Calibrated Data logger

Test procedure:

Operate the tunnel steriliser as per the SOP.

10 number of temperature sensors shall be passed randomly along with the conveyor from the drying zone. Ensure that the entire conveyor area to be covered during mapping. The placement temperature sensors in empty chamber. The natural progression of sensor on the conveyor that occurs during actual running of the tunnel shall be simulated.

Record the set parameters for the sterilization/Depyrogenation cycle to be operated during the test.

Record the position of temperature sensors in representative schematic form.

Connect the probes to suitable data logger, which can scan and print the actual temperatures with respect to time.

Start the data logger to record the actual temperatures within the sterilization zone with respect to time.

When the sterilization / Depyrogenation cycle completes:

When all the temperature sensors cross the cooling zone, Stop the conveyor belt of sterilizing tunnel, switch off the data logger and pull out the probes.

Collect print out from the printer of the tunnel control panel and attach to the annexure-1 with attachment No.

Download the data from the data logger into the computer for data analysis and printing. Review and attach the printouts with attachment No.

Repeat two more consecutive runs to demonstrate sterilization cycle reproducibility.

Acceptance criteria

There should be uniform temperature distribution across the conveyor belt during the hold period.

The temperature at each temperature sensor should be 325°C ± 250C for NLT 1 Minute during the depyrogenation cycle.

Note: The temperature sensors shall be placed in a straight line across the belt, tied to the SS wire, during heat distribution studies.

Heat Penetration Study For Load Chamber

Tools required: Calibrated Data logger

Test procedure:

Operate the tunnel steriliser as per the SOP.

Empty glass vials (as required) shall be fed to the tunnel sterilizer from the vial washing machine.

10 numbers of Vials spiked with a known amount of Endotoxin (Endotoxin indicator vials) as per SOP and 10 numbers of empty vials with temperature sensors shall be placed in the load as depicted below, to simulate normal sterilization and simulated worst condition in a single load. Both the vials with endotoxin and temperature sensors must be placed side by side.

The placement of Endotoxin indicator vials and temperature sensors in empty vials. The vials shall not be tied with wire to keep them together. The natural progression of the vial on the conveyor that occurs during the actual running of the tunnel shall be simulated.

Record the set parameters for the sterilization cycle to be operated during the test.

Record the position of the vials with temperature sensors and vials with Endotoxin in representative schematic form.

Connect the probes to a suitable data logger, which can scan and print the actual temperatures concerning time.

Start the data logger to record the actual temperatures within the sterilization zone concerning time.

During the validation run inspect the vials in the tunnel sterilizer for the following parameters:

Look through the glass window of the tunnel to the following shall be verified

Position of the vials on the conveyor.

Movement of the vial on the conveyor belt.

To inspect the incoming vials to the in-feed turntable of the powder filling machine.

Breakage / Cracks in vials on sterilization.

Presence of any spot on the sterilized vial surface.

When the sterilization cycle completes:

When all the vials, are attached with temperature indicating probe and endotoxin indicator vials, and vials cross the cooling zone, Stop the conveyor belt of the sterilizing tunnel, switch off the data logger, and pull out the probes.

Collect print out from the printer of the tunnel control panel, review, and attach to annexure-1 with attachment No.

Download the data from the data logger into the computer for data analysis and printing. Review and attach the printouts to annexure-1 with attachment No.

Wrap the exposed endotoxin indicator vials with sterile aluminum foil in the filling room and identify them suitably. Send the exposed vials to the Microbiology lab to estimate the quantity of the residual endotoxin as per the SOP. Record the results.

Repeat two more consecutive runs to demonstrate sterilization cycle reproducibility.

Acceptance criteria

There should be uniform temperature distribution across the conveyor belt during the hold period.

The temperature at each temperature sensor should be within ± 250C during the depyrogenation cycle.

The FH value should be more than the value calculated in the FH value calculation sheet proving the sterility assurance by 12-log reduction. (Using assumed D-value and worst case heat resistant spore population)

The temperature distribution is uniform throughout the sterilization period i.e. 325°C ± 250C for NLT 1.0 min.

Endotoxin-spiked vials exposed to the depyrogenation cycle should show more than a 3-log reduction in the endotoxin content when tested.

The conveyor should be packed with vials.

The vial should move on the conveyor belt in an erect condition. No vial should be tilted.

No breakage of the vial should be observed.

No charring spot should be observed on the surface of the vials.

RECORDING OF OBSERVATIONS

Record the observations after the execution of each test procedure, in the annexure  (Recording of Observations For Performance Qualification).

DISCREPANCY AND CORRECTIVE ACTION REPORT

Document any discrepancies observed during the Performance qualification of the equipment in Annexure. Include the corrective actions of the same. When all the discrepancies are satisfactorily resolved or an approved action plan is developed it ensures that the discrepancy will be resolved.

COMPILATION, REVIEW, AND SUMMARY REPORT

Compile and review that all test functions have been completed, reconciled, and attached to this protocol. Verify that the approvals for deviations have been taken and are resolved appropriately to the satisfaction.

Performance Qualification shall be considered acceptable when all the conditions specified in the test procedures have been met.

Prepare the summary report in the annexure (Performance Qualification Report) and submit this for review, approval, and authorization to the Validation Core Team.

APPENDIX

Abbreviations and definitions

AbbreviationDefinitions
PQPPerformance Qualification Protocol
SOPStandard Operating Procedure
QAQuality Assurance
QCQuality Control
NANot Applicable
No.Number
PLCProgrammable Logic Controller

References

SOP for Qualification of Equipment and Utilities

Validation Master Plan

SOP No. QC224 (Recovery Of Endotoxin From Rubber Stoppers, Vials,       Aluminium Containers And Rubber Bungs)

Enclosures

Annexure (Recording Of Observations For Performance Qualification)

Annexure (Performance Qualification Report)

REQUALIFICATION CRITERIA

Requalification criteria are as follows

If any major changes or modifications in the equipment.

Change of cycle program

Inclusion of new load                       

Placement Of Endotoxin Indicator Vials And Vials With Temperature Sensors On The Conveyor
Sensor No.LocationJustification for location selection
1 and 6The left side of the conveyor belt.To verify uniform heat penetration in the vials on the left side of the conveyor belt in the tunnel, which is considered to be the critical area where there may be a possibility of a cold spot because the hot air re-circulation ducts are below the conveyor belt.
4 and 9Towards the left side from the middle of the conveyor belt.To verify uniform heat penetration in the vials across the conveyor belt towards the left side from the middle of the conveyor belt.
2 and 7In the middle portion of the conveyor belt.To verify uniform heat penetration in the vials across the conveyor belt in the middle portion of the conveyor belt.
5 and 10Towards the right side from the middle of the conveyor belt.To verify uniform heat penetration in the vials across the conveyor belt towards the right side from the middle of the conveyor belt.
3 and 8The right side of the conveyorTo verify uniform heat penetration in the vials on the right side of the conveyor belt in the tunnel, which is considered to be the critical area where there may be a possibility of a cold spot because the hot air re-circulation ducts are below the conveyor belt.

Note: For Heat distribution study, only temperature sensors shall be considered.

ANNEXURE -1

Details Of Operational Qualification Report

Report No. /Date Of Authorisation

Identification Of The Executors

S. No.NameDesignation & Department Sign & DateTraining Details
    

Comments:

Measurement of Airflow Velocity

Drying Zone:

Name of the Instrument: Anemometer

Calibration certificate No:______________________ Validity: From:__________To:__________

Calculations:

Minimum Number of measuring locations = 4 locations are decided for measuring velocity.

Acceptance Criteria: Airflow velocity across the HEPA filter should be within the range of 98 ± 20% Feet/Minute.

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Run 1Run 2Run 3AverageAverage of all locations
Location 1      
Location 2    
Location 3    
Location 4    

Hot Zone:

Name of the Instrument: Anemometer

Calibration certificate No:______________________ Validity: From:__________To:__________

Calculations:

Minimum Number of measuring locations = 4 locations are decided for measuring velocity.

Acceptance Criteria: Airflow velocity across the HEPA filter should be within the range of 138 ± 20% Feet/Minute.

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Checked by Sign / Date
Run 1Run 2Run 3AverageAverage of all locations
Location 1       
Location 2    
Location 3    
Location 4    

 

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Checked by Sign / Date
Run 1Run 2Run 3AverageAverage of all locations
Location 1       
Location 2    
Location 3    
Location 4    

Cool Zone:

Name of the Instrument: Anemometer

Calibration certificate No:______________________ Validity: From:__________To:__________

Calculations:

Minimum Number of measuring locations = 4 locations are decided for measuring velocity.

Acceptance Criteria: Airflow velocity across the HEPA filter should be within the range of 118 ± 20% Feet/Minute.

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Checked by Sign / Date
Run 1Run 2Run 3AverageAverage of all locations
Location 1       
Location 2    
Location 3    
Location 4    

 

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Checked by Sign / Date
Run 1Run 2Run 3AverageAverage of all locations
Location 1       
Location 2    
Location 3    
Location 4    

 

Filter No. Filter/ Grill Area (A):
LocationAir velocity in Feet/MinuteAir Flow

F = V x A

CFM

Checked by Sign / Date
Run 1Run 2Run 3AverageAverage of all locations
Location 1       
Location 2    
Location 3    
Location 4    

 Comments:

Differential Pressure Test
Photohelic Gauge IDCalibration DetailsFromWith respect toDifferential pressure in MMWGLimit on display

in mmwc

Certificate No.FromToRun – 1Run – 2Run – 3
Drying zoneVial washing sideEqual to or above 21.2
Hot zone toDrying zoneEqual to or above 25
Sterility testing roomChange room 2Equal to or above 25

Installed Filter System Integrity and Leakage Test (DOP /PAO Test)

Name of the Instrument: Aerosol Photometer

Calibration Certificate No:______________________Validity: From:__________To:__________

Aerosol used:________________________________

Acceptance Criteria: Designated leaks are deemed to have occurred where a reading greater than 10−4 (0.01%) of the upstream challenge aerosol concentration and should be ‘zero’ through mounting joints. Alternative acceptance criteria may be agreed based on the filter efficiency.

S. No.Filter ID No.Efficiency

 %

Upstream Concentration %Downstream Concentration %Mounting joints

%

Drying zone
1
Hot zone
1
2
Cool zone/Stabilizing zone
1
2
3

Airflow Pattern Test

Chemical Used: Titanium Tetra Chloride or Dry Ice

Acceptance criteria:

Air should flow from the higher-pressure zone to the low-pressure zone.

Airflow Pattern/DirectionAirflow toward Pre-filter

Pass/Fail

From (High-pressure zone)To (Low pressure zone)Pass / Fail
Drying zoneVial washing side
Hot / Sterilising zoneDrying zone
Cool zone
Vial filling sideCool zone

Non-Viable Particle Count Test

Stage: Before / After Depyrogenation cycle

Vial Size:

Zone Name: Drying Zone                                                          

Name of the Instrument: Laser-Based Air Borne Particulate Counter.

Calibration Certificate No:___________Validity: From: _________To:_________

Test Conditions: At Rest; Specified Class: ‘A’

Calculations:

Number of locations =  5 locations are decided for sampling

Sample Volume  =3 cycles per location

Acceptance limit: Maximum permitted number of particles/m3 equal to or above 0.5μm: 3500; 5μm: 20

 Observations from raw data

S. No.Checks
1Date of testing
2Date of completion

 

ChecksObservation (Yes / No)
Number of cycles per location is met with the above calculations. 
Number of sampling locations is met with the above calculations. 
Each cycle of each location met the acceptance criteria 
The average of each location is met with the acceptance criteria 
The mean of all locations is met with the acceptance criteria 
95% of UCL complies with the acceptance criteria. 

Zone Name: Hot/Sterilising Zone                                          

Name of the Instrument: Laser-Based Air Borne Particulate Counter.

Calibration Certificate No:___________Validity: From: _________To:_________

Test Conditions: At Rest; Specified Class: ‘A’

Calculations:

Number of locations = 7 locations are decided for sampling

Sample Volume  =  3 cycles per location

Acceptance limit: Maximum permitted number of particles/m3 equal to or above  0.5μm: 3500; 5μm: 20 

Observations from raw data

S. No.Checks
1Date of testing
2Date of completion

 

ChecksObservation (Yes / No)
Number of cycles per location is met with the above calculations. 
Number of sampling locations is met with the above calculations. 
Each cycle of each location met the acceptance criteria 
The average of each location is met with the acceptance criteria 
The mean of all locations is met with the acceptance criteria 
95% of UCL complies with the acceptance criteria. 

Zone Name: Cool Zone                                      

Name of the Instrument: Laser-Based Air Borne Particulate Counter.

Calibration Certificate No:__________Validity: From: _________To:_________

Test Conditions: At Rest; Specified Class: ‘A’

Calculations:

The number of locations =15 locations are decided for sampling

Sample Volume = 3 cycles per location

Acceptance limit: Maximum permitted number of particles/m3 equal to or above  0.5μm: 3500; 5μm: 20 

Observations from raw data

S. No.Checks
1Date of testing
2Date of completion

 

ChecksObservation (Yes / No)
Number of cycles per location is met with the above calculations. 
Number of sampling locations is met with the above calculations. 
Each cycle of each location met with the acceptance criteria 
Average of each location is met with the acceptance criteria 
Mean of all locations is met with the acceptance criteria 

 Heat Distribution Study For Empty Chamber

DEPYROGENATION CYCLE PARAMETERS
Parameter
PLC set point
Parameter
PLC set point
Set point (deg C)HZ over shoot (deg C)
Conveyor start temperature (deg C)Conveyor stop temperature (deg C)
Conveyor speed (mm/min)CZ over shoot (deg C)
Data logging time (min)Night mode HZ temp (deg C)
Recipe type

Observations from Printouts:

ChecksRun – 1Run – 2Run – 3
Date of testing   
Date of completion   
Done by   

 

ChecksObservation Yes / No
Run – 1Run – 2Run – 3
The temperature at each temperature sensor should be within ± 250C during the depyrogenation cycle.   
The temperature distribution is uniform throughout the sterilization period i.e. ± 250C to set temperature for at least 3.0 min.   
Conveyor speed (mm/Min) is observed as per the set point throughout the cycle.   
A nonviable particle count has been taken after validation runs and complies with the acceptance criteria.   

  Heat Penetration Study

DEPYROGENATION CYCLE PARAMETERS
Parameter
PLC set point
Parameter
PLC set point
Set point (deg C)HZ over shoot (deg C)
Conveyor start temperature (deg C)Conveyor stop temperature (deg C)
Conveyor speed (mm/min)CZ over shoot (deg C)
Data logging time (min)Night mode HZ temp (deg C)
Recipe type

Observations from Printouts:

ChecksRun – 1Run – 2Run – 3
Vial type/size   
Date of testing   
Date of completion   
Done by   

 

ChecksObservation Yes / No
Run – 1Run – 2Run – 3
The conveyor is packed with vials during the run.   
Is the vial moved on the conveyor belt in erect condition? No vial should be tilted.   
Any breakage of the vial was observed during the run.   
The temperature at each temperature sensor is within ± 250C during the depyrogenation cycle.   
The temperature distribution is uniform throughout the sterilization period i.e. ± 250C to set temperature for at least 3.0 min.   
Conveyor speed (mm/min) is observed as per the set point throughout the cycle.   
Exposed endotoxin indicators are meeting the minimum 3-log reduction   
Non viable particle count has taken after validation runs and complies the acceptance criteria.   

Discrepancy And Corrective Action Report

ANNEXURE -2

Heat Penetration Study For Load Chamber

Spiking of Endotoxin Vials

Vial Type/ Size:                                                              

Endotoxin Indicators
Lot No.Amount
Expiry DateReconstitution on
LRW Details
LRW Lot No.:Expiry Date:
Date of Opening:
Spiking details
Micropipette ID:LAF ID:
Validation CSE Potency:Reconstitution:
Spiked volume:Number of Spiked vials:
Done By:

  Recovery of Spiked Endotoxin

 Confirmation Of Labelled Claim Sensitivity Of The Lysate

LRW DetailsLAL DetailsControl Standard Endotoxin Details
LRW Lot No.LAL Lot No.Lot No.
Expiry DateSensitivityExpiry Date
Date of OpeningDate of ReconstitutionConc.
Expiry DateReconstituted on
Endotoxin Indicators
Lot No.Amount
Expiry DateReconstitution on

Control Standard Series

Tube No.LRW ( ml)Vol of CSE added from TubeFinal CSE Concentration
01   
02   
03   
04   
05   
06   

Observation:

Time of Incubation:                                   Time of Observation  :

Temp. at Incubation:                                   Temp. at Observation        :

Replicate No.Observation at different concentrationsEnd PointLog 10

End Point

– ve Control

(0.1 ml LRW + 0.1 ml lysate)

2 λλλ/2λ/4
I       
II       
Mean of log  10 End Point    
Geometric Mean = Antilog 10 of Mean End Point  

Remarks:  The geometric Mean End Point concentration is within the / Not within the ± two-fold of the labeled claim sensitivity of the lysate.

Done By:

RECOVERY OF ENDOTOXIN IN UNEXPOSED SPIKED VIALS

No. of Unexposed vial used for determining the recovery =  01

Endotoxin Concentration Spiked on each vial= 10000 EU /vial

The volume of LRW required for dilution  = 4.0 ml

The total concentration in the vial will be 10000/4 =2500 EU/ ml

Dilutions:

Tube No.The volume of LRW addedVolume of Endotoxin ConcentrationsFinal ConcentrationDilution
0.9 ml0.1 ml of 2500 EU/ml250 EU /ml1: 40
0.9 ml0.1 ml of Tube No.125 EU / ml1: 400
0.9 ml0.1 ml of Tube No.22.5 EU / ml1: 4000
1.8 ml0.2 ml of Tube No.30.25 EU / ml1: 40000
1.0 ml1.0 ml of Tube No.40.125 EU / ml1: 80000
1.0 ml1.0 ml of Tube No.50.06 EU / ml1: 160000

Observation:

Time of Incubation:                                          Time of Observation:

Temp. at Incubation:                                          Temp. at Observation:

DilutionSampleVol. of SampleVol. of LysateResult
·        – ve ControlTest100 µl of LRW100 µl
Duplicate100 µl of LRW100 µl
·        1 : 40 000

 

Test100 µl100 µl
Duplicate100 µl100 µl
·        1 : 80 000

 

Test100 µl100 µl
Duplicate100 µl100 µl
·        1 : 160000

 

Test100 µl100 µl
Duplicate100 µl100 µl

ENDOTOXIN CONTENT IN EXPOSED VIALS AFTER DEPYROGENATION

Concentration of Endotoxin Spiked on each vial = 10000 EU / vial.

Assuming that after depyrogenation a three-log reduction must have taken place, the total concentration on each vial will be = 10 EU / vial.

The volume of LRW used for Dilution = 4.0 ml/vial

Therefore the total concentration in the vial will be = 2.5 EU / ml

Dilutions:

Tube No.The volume of LRW addedVolume of Endotoxin ConcentrationsFinal ConcentrationDilution
1.1.8 ml of LRW0.2 ml of 2.5 EU / ml0.25 EU /ml1: 40
2.1.0 ml of LRW1.0 ml of 0.25 EU / ml0.125 EU /ml1: 80

 

DilutionSampleVol. of SampleVol. of Lysate
·        1: 40Test100 µl100 µl
·        1: 40Duplicate100 µl100 µl
·        1: 80Test100 µl100 µl
·        1: 80Duplicate100 µl100 µl

Observation:

Time of Incubation:                                    Time of Observation           :

Temp. at Incubation:                                   Temp. at Observation        : 

Vial No.Dilution  1: 40Dilution 1: 80Vial No.Dilution 1: 40Dilution 1: 80
TestDuplicateTestDuplicateTestDuplicateTestDuplicate

 ESTIMATION OF ENDOTOXIN REDUCTION FOR RUN NO._______

Recovered endotoxin per = Reciprocal of the last dilution which Exposed vials were positive X lambda (Sensitivity of the Lysate).

Last positive Dilution =…………….

Therefore the reciprocal will be         =…………….

Sensitivity of the Lysate = 0.125 EU / ml

=  …………….  X 0.125 EU/ ml

=  ……………….. EU / vial

Recovered endotoxin per = Reciprocal of the last dilution which

The unexposed vial was positive X lambda (Sensitivity of the Lysate).

  • Last positive Dilution =…………….
  • Therefore the reciprocal will be         =…………….
  • Sensitivity of the Lysate = 0.125 EU / ml

=   ……………….  X 0.125 EU/ ml

=  ……………….. EU / vial

therefore the amount of endotoxin reduced after depyrogenation

= log (b) –  log (a)

= log …………-  log ……. ….

=  ……………….log reduction

Anti log of (log reduction)              =   ……………….fold reduction

INTERPRETATION:

There is a greater / less than 3 log reduction in endotoxin in the Depyrogenated vial. Hence depyrogenation cycle was successful / not successful. 

Pharma More Jobs and post Please click here

About Pharmaceutical Guidanace

Ms. Abha Maurya is the Author and founder of pharmaceutical guidance, he is a pharmaceutical Professional from India having more than 18 years of rich experience in pharmaceutical field. During his career, he work in quality assurance department with multinational company’s i.e Zydus Cadila Ltd, Unichem Laboratories Ltd, Indoco remedies Ltd, Panacea Biotec Ltd, Nectar life Science Ltd. During his experience, he face may regulatory Audit i.e. USFDA, MHRA, ANVISA, MCC, TGA, EU –GMP, WHO –Geneva, ISO 9001-2008 and many ROW Regularities Audit i.e.Uganda,Kenya, Tanzania, Zimbabwe. He is currently leading a regulatory pharmaceutical company as a head Quality. You can join him by Email, Facebook, Google+, Twitter and YouTube

Check Also

Unlocking Success with User Requirement Specification: Coating Machine URS

Unlocking Success with User Requirement Specification: Coating Machine URS In any project or system development, …