- PURPOSE:
- To describe the Operational Qualification of Vertical Laminar Reverse flow Containment Station, its accessories and to define the specification of the system in order to:
- Ensure that the equipment meets the Operational/Design limits as per user requirements.
- Ensure that the equipment will be operationally qualified in accordance with current Good Manufacturing Practices
- SCOPE:
- The scope of this document applies to the operational qualification of Vertical Laminar Reverse flow Containment Station.
- RESPONSIBILITIES:
- It is the responsibility of the Manufacturer to prepare the operational qualification and identify the test parameters to be studied for qualifying the Vertical Laminar Reverse flow Containment Station operationally.
- It is the responsibility of the client to check and approve the Operational qualification.
- PROCEDURE:
- The following requirement / practices apply to Vertical Laminar Reverse flow Containment Station Operational Qualification activities:
- To verify the components design parameters.
- Review the preventive maintenance procedures, cleaning procedures and general Operation procedure to ensure that they are comprehensive for reliable performance of the equipment.
- OPERATIONAL QUALIFICATION TESTS:
- The table below lists the tests to be performed as part of the Operational Qualification phase.
TEST NUMBER | CRITICAL FEATURE |
5.1 | Main Panel/Control Panel Testing |
5.2 | Power & Communication Failure Recovery Verification |
5.3 | Air Velocity Test |
5.4 | HEPA Filter Integrity Test |
5.5 | Differential Pressure Test across Filters |
- Main Panel / Control Panel Testing.
- Purpose – To verify that the response of the equipment at the input from various Pushbutton / Switches on control or main panel is as per the system design.
- Test equipment – None Required.
- Procedure –
- Give inputs from various Push buttons & Switches on Control Panel / Main Panel & observe the Response from the machine.
- Acceptance Criteria –
- The equipment will respond as mentioned in the target column of the table given below.
- Take dry run of the equipment to ensure that all controlling parameters & functions are reproducible.
- Test Results
Input | Target | Actual | Test Done by | Date |
Main Panels main switch switched ON. | Control ON indicating lamp will glow. | |||
Press ON Switch for Tube light | Tube light will glow. | |||
Press ON Switch for Equipment | Equipment will start. Differential Pressure across HEPA, Intermediate and Prefilter will rise. |
- Conclusion:
- Power & Communication Failure Recovery Verification
- Rationale – To verify that in the event of a power loss or communications failure, the equipment will stop in safe condition.
- Test equipment – None Required.
- Procedure–
- Operate the equipment in automatic mode or as directed in the User Manual
- While the equipment is operating, shut down the power to the main control panel. Record if the equipment stops in a safe and secure condition.
- Wait for 5 minute then restore power to the equipment
- Check whether system is start running once the power is restored.
- The system is not starting of its own, restart the equipment.
- Acceptance criteria –
- At step 5.2.3.2 the equipment stops in a safe and secure condition.
- At step 5.2.3.4, the equipment should not start of its own after the power is restored without user permission.
- At step 5.2.3.5, the equipment can be restarted with NO problems.
- Power and Communication Failure Recovery test results
Test | Results | Meets Test
(Yes / No) |
Test Done by | Date |
Main Power Shut Down | Equipment stops in a safe and secure condition. | |||
Main Power Restored | Equipment is not starting of its own without user permission | |||
Equipment can be restarted with NO problems. |
- Conclusion:
- Air Velocity Test
- Rationale – This test covers testing to determine air velocity and uniformity of air velocity at the work location in a clean air device.
- Test equipment – Air velocity meter.
- Procedure–
- Switch ON the equipment by pressing ON/OFF button and let the system to stabilized for 5-10 minute.
- Take reading in a plane parallel to and 6 inches downstream of the HEPA filters or the protective grille over the filters.
- Take reading at four corners and centers (Refer Fig.1) for minimum of 10 sec. and note the values in the table.
LC2
LC1 |
C |
RC2
RC1 |
Fig.1
- Acceptance criteria –
- The air velocity must be 90 ± 20 FPM.
- Air Flow Velocity Test Results–
- Name of Measuring Equipment:
- Instrument Sr. No.:
- Calibration Due Date:
HEPA
Filter No. |
LC1 | LC2 | RC1 | RC2 | C | Mean | Meets Test
(Yes/No) |
Checked By | Date |
F1 | |||||||||
F2 | |||||||||
F3 | |||||||||
F4 | |||||||||
F5 | |||||||||
F6 |
- Note: Mean = (LC1+ LC2 + RC1+ RC2 +C) / 5
- Conclusion:
- HEPA Filter Integrity Test
- Rationale – To verify that the filter system is properly installed and leakage has not developed.
- Test equipment – Aerosol Generator and Photometer
- Procedure:
- Ensure the LAF is running for minimum 1 hour.
- Operate the Aerosol generator as per its operation manual.
- Introduce the aerosol before HEPA at a concentration in the range of 10-100 mg/ m3.
- Hold the Photometer probe about 4-5 cm. away from the filter face or the frame structure.
- Scan the entire downstream face of each filter at a scan rate of 5cm/s (for square probe of 3cm X 3cm) and 15cm2/s for rectangular probe.
- Acceptance criteria – Leakage factor is not more than 0.03%.
- Note: Air velocity test should be confirmed before this test.
- Replace any HEPA filter leakage (less then 5% of filter area) with silicone sealant. Eliminate leaks in the gasket frame area by re-tightening the filter hold-down clamps.
- HEPA Filter Integrity Test Result
- Name of the Measuring Instrument:
- M/C Serial No.:
- System No.:
- Room Name:
Sr. No. | Terminal No. | DOP1- Cold DOP Charged Before HEPA Filter | DOP 2 – Penetration after HEPA filter |
1 | F1 | 100% | _____% |
2 | F2 | 100% | _____% |
3 | F3 | 100% | _____% |
4 | F4 | 100% | _____% |
5 | F5 | 100% | _____% |
6 | F6 | 100% | _____% |
- Conclusion:
- Differential Pressure Test Across Filters
- Rationale – To verify the differential pressure across HEPA, Intermediate and Pre filter.
- Test equipment – Magnehalic Pressure Gauge inbuilt with the equipment.
- Procedure:
- Start the equipment as per operational manual and allow the blower to get stabilized for 5-10 minutes.
- Note down differential pressure across HEPA, Intermediate, Pre filter from respective Magnehalic Pressure Gauge.
- Acceptance criteria – As mention in the test result table.
- Differential Pressure Test Results
Test | Acceptance Criteria | Results | Meets Test
(Yes / No) |
Checked By | Date |
Differential Pressure Across Prefilter | 1-3 mm WG | ||||
Differential Pressure Across Intermediate filter | 1.5-5 mm WG | ||||
Differential Pressure Across HEPA | 8-14 mm WG |
- Conclusion:
- Operational Qualification Tests Status
- The table below lists the tests performed and related results.
Test Number
|
Critical Feature
|
Pass | Fail | Deviation Found | |
Yes | No | ||||
5.1 | Main Panel/Control Panel Testing | ||||
5.2 | Power & Communication Failure Recovery Verification | ||||
5.3 | Air Velocity Test | ||||
5.4 | HEPA Filter Integrity Test | ||||
5.5 | Differential Pressure Test across Filters |
- LIST OF STANDARD OPERATING PROCEDURES
Sr. No. | Description | SOP No. | Verified By | Date |
1 | Operating Procedure of Vertical Laminar Reverse flow Powder Containment Station. | |||
2 | Cleaning Procedure of Vertical Laminar Reverse flow Powder Containment Station. | |||
3 | Preventive maintenance of Vertical Laminar Reverse flow Powder Containment Station. |
- Data Analysis, Summary of OQ & Recommendations
- AMENDMENT RECORD
Sr. No. |
Item Name |
Remarks |
Signature & Date |
- Note: Any changes made in the system must be recorded in this sheet.
- CONCLUSION
- More Jobs UpdatesVisit@ https://pharmaguidances.com