URS of De-Dusting Machine
S. No. |
Table of Contents |
1.0 | General |
2.0 | Salient Features |
3.0 | Operational Requirements |
4.0 | Utilities |
5.0 | Maintenance |
6.0 | Commissioning and Documentation |
7.0 | Training |
8.0 | Packaging |
9.0 | Deviations |
10.0 | Delivery |
TECHNICAL
S. No. | Parameters | Required Specifications |
1.
1.1 |
GeneralEquipment No. |
|
1.2 |
Description |
Portable unit for Tablets de-dusting. |
1.3 |
Use |
The equipment will be used for online removing of dust adhered to the tablets. |
1.4
|
Field Identification |
To be installed in Compression area.
Allocated floor space for the equipment to be specified by supplier. (i) Room Temperature NMT 300C and RH less than 60% (ii) Non flame proof area |
1.5 |
Glossary |
As per Annexure-1 |
2.
2.1 |
Salient FeaturesGeneral |
|
2.2 |
Material of Construction |
All the contact parts should be of SS 316 and non-contact parts shall be of SS 304. |
2.3 | Electrical Construction | Non flameproof. |
3. |
Operational requirement |
The system shall operate with a minimum of operator involvement. Operation shall be safe from an operator and environmental standpoint. The system shall be operated locally at the equipment itself.
·Height of machine (Supplier to specify). ·Control panel shall contain ON and OFF switches. |
3.1
|
Control Parameters |
·Vibration of the machine shall be adjustable.
·Working height of the machine shall be adjustable. ·Machine shall have provision to connect with Dust Extraction System. ·Machine shall have dust collection box. |
3.2
|
Power failure / recovery |
In the event of a power failure, the system shall protect product against damage. The system will stop in a safe mode automatically upon loss of electricity and shall not require operator intervention to re-start. |
4. | Utilities | To provide utilities at ONE POINT is user’s responsibility. |
5. | Maintenance | Supplier should provide the following maintenance instructions,
i. Operation and Maintenance manuals along with as built drawings ii. Daily checks on machine iii. Cleaning procedures |
6.
|
Commissioning and Documentation
|
· IQ/OQ/PQ to be completed by the supplier along with company representatives.
· The Supplier to demonstrate the Performance of the machine at site as per agreed terms. · Exact use in the equipment designed. · Calibration certificates of all the instruments used having traceability to NPL / NIST. ·Performance certificates of Tests conducted. · At manufacturers end for Motors / Gear Box / Fan and other critical bought out items with Serial nos. |
7.
7.1 |
Training
Start up support |
Supplier to train the respective technical associates of company on operation, maintenance and cleaning of the equipment wherever applicable. |
7.2 |
Post start up support |
Telephone / Fax / E mail ID / Address
Replacement parts availability list (normal lead times shall be listed) System improvements (supplier shall notify user of any improvements) |
8. | Packaging | |
9. | Deviations | Any deviation from URS shall be highlighted. |
10. | Delivery | Company adress |
Annexure-1
GLOSSARY
URS | User requirement specifications | |
DQ | Design Qualification | |
IQ | Installation Qualification | |
OQ | Operational Qualification | |
PQ | Performance Qualification | |
0C | Degree Celsius | |
PLC | Programmable Logic Control | |
RH | Relative Humidity | |
Pa | Pascals | |
NPL | National Physical Laboratory | |
NIST | National Institute of Standards & Technology | |
MS | Microsoft | |
SCADA | Supervisory Control and Data Acquisition | |
SS | Stainless Steel | |
MMI | Man Machine Interface |