Objective: To lay down a procedure for Handling of Raw & Packaging Materials under Re-Test due.
Scope: This SOP is applicable to all raw & packaging materials under retest due in warehouse.
Responsibility:
Warehouse personnel shall be responsible for intimating Quality control about the retest due.
Quality control personnel shall be responsible for analysis and approval / rejection of material under retest due.
Accountability: HOD-Warehouse and HOD-QA/QC shall be responsible for implementation & compliance of this SOP.
Procedure:
Check the materials under re-test dates given by QC on the GRN & Re-Test date shall be recorded in Re-Test Material Verification Record.
The warehouse personnel shall raise the Re-Test request of Raw & Packaging Material with existing stock along with the actual receipt quantity & GRN No. to QC for sampling the material(s).
The container(s) / pack(s) of the material shall be transferred to the respective Quarantine affixed with “QUARANTINE” label duly filled with current available quantity for re- test & signed by warehouse personnel.
The previous Quarantine label along with Approved status label shall be defaced with permanent black marker pen & new Quarantine label shall be affixed nearby defaced label.
The material to be retested in the next month shall be verified with existing stock recorded from the Material Stock Card.
The Intimation / Communication for retest shall be prepared by warehouse personnel through Re-Test Request of Raw & Packaging Material. The Re-Test Request shall be send to QC on the Re-Test date mentioned in the GRN.
The QC personnel take the sample of the respective material & after final analysis, the “APPROVED” / “REJECTED” label as applicable shall be displayed on the container(s) / Pack(s) of the material.
Approved / Rejected status of materials shall be provided by Quality Control through Re-Test Request of Raw & Packaging Material along with respective label.
Warehouse personnel shall transfer the material(s) in their respective storage area as per status provided by QC.
Note: – The materials under Re-Test date (To be used within seven days) provided by QC shall only be tested at the time of requirement / production plan & not to tested time & again if Re-evaluation date of that material already passed.
DQ (DESIGN QUALIFICATION) DOCUMENT FOR AHU- 4000 CFM / 150 mm wg - SP To… Read More
ENVIRONMENTAL FAILURE (STEPS TO BE TAKEN IN CASE) PURPOSE: To lay down a procedure for… Read More
SOP ON CAPA (CORRECTIVE ACTION AND PREVENTIVE ACTION) PURPOSE: To lay down the standard operating… Read More
SOP OF PRODUCT RECALL PURPOSE: This procedure covers transmission of information by means of a… Read More
(DQ)DESIGN QUALIFICATION FOR PURE STEAM GENERATION SYSTEM DQ- The Author signature indicates that this document… Read More
Design Qualification (DQ) Protocol Form Fill Seal Blow-Fill-Seal (BFS) technology is a manufacturing technique used… Read More