MAINTENANCE OF BOREWELL PUMP

  • OBJECTIVE           
  • To lay down a procedure for Maintenance of Bore well Pump                  
  • SCOPE
  • This SOP is applicable to bore well Pump            
  • RESPONSIBILITY
  • Technical Supervisor / Engineer       
  • ACCOUNTABILITY
  • Sr.Executive / Manager                    
  • PROCEDURE
  • Monthly Maintenance
  • Clean the contactors with CTC / CRC
  • Ensure the pump load should be in between 7.5-10 Amps
  • Ensure no water leakages from pipe lines.
  • Ensure cable glands are tight.
  • Ensure the earthing, which is connected to the pump, should also be connected to earth grid by checking with earth megger.
  • Clean the control panel with air blower.
  • Put a Tick mark in Monthly Check Sheet after completion of each activity. If it is not O.K put a cross (X) in Monthly Check Sheet indicating the reason in remarks column.
  • Immediately inform to the concern superior if it is not O.K (X) and take necessary corrective action as per the advice.
  • Any such deviations should be maintained in the Machine History Cord along with necessary corrective action and its complaints there of.
  • Yearly Maintenance
  • Check the valve function by opening & closing and ensure the water is flowing through the valve during open condition and water should not flow during closing condition.
  • Overhaul the pump.
  • Put a Tick mark  in Yearly Check Sheet and repeat the above mentioned procedure.
  • Forms and Records (Annexures)
  • Not Applicable
  • Distribution
  • Master copy –  Quality Assurance
  • Controlled copies- Quality Assurance, Production, Quality Control
  • History
    Date Revision Number
    Reason for Revision

     

    00 New SOP

     

 

 

 

 