- PURPOSE:
- To describe the Installation Qualification of Raw Gelatin Storage Vessel its accessories and to define the Specification of the system in order to:
- Ensure that the equipment meets the specification as per Design Qualification.
- Aid verification of the installation as per equipment general arrangement Drawing.
- Ensure that the system installation meets acceptance criteria.
- Ensure that the equipments will be installed in accordance with current Good Manufacturing Practices.
- SCOPE:
- The scope of this document applies to the installation qualification of Raw Gelatin Storage Vessel.
- RESPONSIBILITIES:
- It is the responsibility of the Manufacturer to perform all the specifications verification checks and tests with respect to installation qualification and compiling data in co-ordination with client.
- It is the responsibility of the client to check and approve the installation qualification.
- PROCEDURE:
- The following requirement / practices apply to Raw Gelatin Storage Vessel Installation Qualification activities:
- Verify that systems are installed in accordance with approved engineering drawings and documents, which shall include the following.
- General arrangement drawing.
- Installation specification.
- Equipment manuals
- Verify that the equipment and instrumentation are clearly described as per vendor, model, capacity, materials of construction and any critical criteria.
- Verify that major components are tagged or labelled with a unique ID number.
- INSTALLATION QUALIFICATION TESTS:
- The table below lists the tests to be performed as part of the Installation Qualification phase.
TEST NUMBER | CRITICAL FEATURE |
5.1 | Documents & Drawings Verification |
5.2 | Verification of Technical Specification for
In-House & sub-components / bought out items |
5.3 | Material of construction verification |
- Documents & Drawings Verification
- Rationale – To verify that the documentation provides complete and correct technical references and permits servicing of the units.
- Test equipment – None Required.
- Procedure :
- Verify that the required documents and drawings listed in the table 5.1.5 is available.
- Review the documents and drawings for completeness and exactness with the installed units.
- Attach the copies of the drawings to this document or reference the location from where they can be easily retrieved.
- Any items in the installation, which are not conforming to the corresponding drawings, must be commented on in the appropriate space. List the non-conformances and the reasons for them in an attachment if necessary.
- Acceptance Criteria:
- The documents must be accurate and complete.
- The drawing information must correspond to the physical installation.
- Documentation Verification Results.
Sr. No. | Description | Document No. | Sign. | Date |
1 | Installation, Operation and Maintenance Manual | |||
2 | General arrangement drawing |
- Conclusions / Comments:
- Verification of Technical Specification for In-House & sub-components / Bought out items
- Purpose – To verify that each major component of the Raw Gelatin Storage Vessel are present and identified.
- Test Equipment – None Required
- Procedure
- Confirm that identification nameplates have been applied to the units and that these indicate the following (where applicable).
- – Type
- – Identification (Tag) No.
- – Manufacturer
- – Model Number
- Confirm that the various components of Raw Gelatin Storage Vessel are present and tagged as per specifications and drawings, in the proper number and configuration.
- Note any deviations or discrepancies and recommend follow up action if required.
- Acceptance Criteria – All units and parts specified in design qualification and on latest revision of drawings must be present, documented and tagged.
- Major Components Results
Description | Specification | Meets
Spec. (Yes/No) |
Verification Source | Sign. | Date |
|
|||||
Name | Raw Gelatin Storage Vessel | ||||
Surface Finish | mirror (Internal)
Matt (external) |
||||
Overall Dimension | 900 mm (D) X 1130 mm(H) | ||||
Nozzle | 02 Nos.
N1 : Outlet connection N2 : Vent connection |
||||
Main Shell | Shell : 760 X 180 X 2.5 mm Heads : 1.6 mm (T)
Detachable flat cover on top and 2.5 mm (T) conical dish at bottom |
||||
Support | AISI 304 legs (04 Nos.) with SS castor wheel | ||||
Capacity | Working :- 150 L
Gross :- 165 L |
||||
MOC | Contact :- AISI 316 L
Non – Contact :- AISI 304 Gasket:- Silicon |
||||
2. Butterfly Valve | |||||
Type | Manual Butterfly Valve with triclover ends | ||||
Make | Mondentic | ||||
Sr. No. | 525 | ||||
Size | 50.80 mm | ||||
MOC | AISI 316 L | ||||
Gasket | EPDM | ||||
3. Ball Valve for Vent | |||||
Type | Manual Ball Valve with triclover ends | ||||
Make | Mondentic | ||||
Sr. No. | 306/06 | ||||
Size | 3/4” | ||||
MOC | SS 316 L | ||||
4. Castor Wheel | |||||
MOC | SS castor with PU coated nylon wheel | ||||
Type | Pin Mounted | ||||
Qty. | 04 Nos. |
- Conclusions / Comments:
- Material of Construction Verification
- Rationale – To verify that all assembly of Raw Gelatin Storage Vessel has been manufactured as per the specification provided by the customer based on the MOC certificates supplied by the vendor / moly testing unit.
- Test equipment – Moly testing unit (To identify AISI 304 and AISI 316 L materials)
- Procedure:
- Put a drop of Molybdenum solution on the material to be tested.
- Take battery & keep anode at one end of the material and cathode at Moly drop.
- If the solution turns pink and stays for around one minute, then it is AISI 316 L & if the solution turns pink and immediately vanishes, then it is AISI 304.
- Acceptance Criteria – All material of construction for the Raw Gelatin Storage Vessel shall meet the MOC provided in Design Qualification.
- Material of Construction verification Results
Part Description & Size | Material | Meets
Spec. (Yes/No) |
Verification Source | Sign. | Date |
Main Shell, 2.5 mm | AISI 316 L | ||||
Top Cover, 1.6 mm | AISI 316 L | ||||
Bottom Cone, 2.5 mm | AISI 316 L | ||||
Pipe for Leg, 40 NB x Sch.10 | AISI 304 | ||||
Rod for N1, 75 mm | AISI 316 L | ||||
Rod for N2, 35 mm | AISI 316 L | ||||
‘o’ Ring for T/C, 2” | Silicon |
- Conclusions / Comments:
- Installation Qualification Tests Status
- The table below lists the tests performed and related results.
Test Number
|
Critical Feature
|
Pass | Fail | Deviation Found | |
Yes | No | ||||
5.1 | Documents & Drawings Verification | ||||
5.2 | Verification of Technical Specification for In-House & Sub-contract / bought out items. | ||||
5.3 | Material of Construction Verification |
- Data Analysis, Summary of IQ & Recommendations
- AMENDMENT RECORD
Sr. No.
Item Name
Remarks
Signature and Date
- Note: Any changes made in the system must be recorded in this sheet.
- CONCLUSION