- CLEANING OF WATER OVER HEAD TANKS & SUMPS
- OBJECTIVE
- To lay down a procedure for Cleaning of Water Over Head Tanks and Sumps
- SCOPE
- This SOP is applicable to Water Over Head Tanks and Sumps.
- RESPONSIBILITY
- Technical Supervisor / Engineer
- ACCOUNTABILITY
- Sr.Executive / Manager
- PROCEDURE
- Obtain work permit for carrying out cleaning.
- Ensure that all safety precautions are taken while cleaning.
- Drain the water from tank by opening outlet valve and drain valve / drain plug.
- Close the inlet valve of the OverHead.
- Clean the tank thoroughly with brush and cleaning agents and ensure that the buttom of sidewalls is free from Algae and tank is free from foreign material.
- Take sufficient quantity of raw water, clean thoroughly and drain out.
- Top up OverHead tank with fresh water.
- Ensure that there are no water leakages and smooth functioning of float valves.
- Close Dummy plugs and drain valve.
- Open the inlet and outlet valves of Over Head Tank.
- Close the manhole of the Over Head Tank.
- Forms and Records (Annexures)
- Annexure – I
- Distribution
- Master copy – Quality Assurance
- Controlled copies- Quality Assurance, Production, Quality Control
- History
Date Revision Number Reason for Revision – 00 New SOP
Annexure – I
SL. NO | DESCRIPTION | LOCATION | CAPACITY IN KL |
1 | Over Head Tank – 1 | Production Block | 50.0 |
2 | Over Head Tank – 2 | Production Block | 50.0 |
3 | Chilled Water Make Up Tank | Production Block | 1.0 |
4 | Neocota Scrubber Tank – 1 | Production Block | 2.25 |
5 | Neocota Scrubber Tank – 2 | Production Block | 2.25 |
6 | Ganscota Scrubber Tank – 1 | Production Block | 2.25 |
7 | Ganscota Scrubber Tank – 2 | Production Block | 2.25 |
16 | Cooling Tower Make up Tank | Service Block | 60.0 |
17 | Cooling Tower Sump – 1 | Service Block | 40.0 |
18 | Cooling Tower Sump – 2 | Service Block | 40.0 |
19 | D.M. Raw Water Sump | Service Block | 60.0 |